Assisted the City staff in designing the completion of a stormwater pump station to empty the dual-use detention basin that had been constructed as a feature of the park. Calculated the required pumping rates to meet various requirements and confirmed the pump selection. Prepared skeleton designs of the valve vault and piping systems for installation by City staff. The work was performed by City staff, augmented by contractors, on an expedited basis in just 12 weeks to allow the park to open on schedule.